A Key supplier of access solutions to all sectors of the construction industry

National House nears completion.

30 January 2015

 Apex Scaffolding are on the final stretch of erecting National House in Exeter for Kier Construction.

Due to the location of the site and proximity to very busy roads and pavements in the centre of Exeter it has been a challenge throughout.

With assistance from Kier and Devon Highways with complex design input from Optima Scaffold Design.

Apex erected a beam on beam cantilevered section complete with protection fan directly over the road.

This was achieved on 2 successive Sunday mornings with a Section 171 partial temporary road closure, very early starts for our team of dedicated scaffolders and a myriad of signs, cones and pedestrian barriers to ensure that the delays to the flow of traffic and pedestrians were kept to a minimum.